
Agnico Eagle
Challenge
In the tunnels of the Agnico Eagle Laronde gold mine, 2.62
kilometers below the surface of the earth, it’s a challenging
environment. Air enters the mine through multiple fresh air openings,
circulates through the underground tunnels filled with workers and
machinery, and returns to the surface through exhaust airways.
Extreme conditions in the exhaust airways, including high temperatures
and humidity levels, dust filled air, machine exhaust and hot, dirty
water, as well as space limitations, make chiller operating conditions
a
definite challenge.
Selected for their
high-temperature operation, three Trane 1000-ton chillers were
installed in the mine to keep workers comfortable. Not designed for
the harsh mine environment, the chillers failed, with the extreme
conditions causing surging, never seen before by the company’s
engineers. When the same unit failed for the second time within
eighteen months, the Agnico Eagle technician called Trane engineers
for help.
Solution
Trane representatives, including members of the engineering team, visited the Agnico Eagle mine in Quebec to try to determine the cause of the chiller failures. They took the failed parts back to Trane facilities in LaCrosse, Wisconsin, for analysis and provided Agnico Eagle with a full report. The broken parts were replaced, including changing a set of guide vanes to one more suitable for the extreme environment.
Troubleshooting issues, planning for expansion
While Trane worked to solve the cause of the chiller failures,
Agnico Eagle planned their next mine extension, which would go deeper
into the earth. Appreciating Trane’s honest, straightforward approach
throughout the troubleshooting and solution finding process, Agnico
Eagle agreed to consider Trane for the new leg of their mine, but only
under the condition that they could first discuss the project with the
Trane engineering team.
Custom designed for extreme conditions
A customer visit was arranged to the Trane facilities in
LaCrosse, Wisconsin, which included a meeting with the Trane
engineering team and a plant tour. Agnico Eagle management was able to
ask questions and discuss the project fully. After the meeting, Agnico
Eagle was convinced that the previous problems had been resolved, that
Trane could build a “custom” unit that would operate under the extreme
mine conditions and that Trane chillers were the most reliable on the
market for this kind of project. Five Trane 1300-ton CenTraVac™
centrifugal chillers were purchased to keep Agnico Eagle’s four shifts
of workers comfortable in the new mine extension.
Overcoming challenges, improving safety
The five CenTraVac chillers were shipped to Agnico Eagle for
installation in the mine extension. The installation crew dismantled
the chillers into three pieces and put them on a slate, which was
pulled down a thirty-mile spiral ramp until it reached the case where
they would be placed. Knowing that a refrigerant leak would be cause
for evacuation, the Trane team took extra safety precautions as they
worked. Safety features were also paramount for the equipment. With
the Trane CenTraVac chillers operating at internal pressures lower
than the atmospheric pressure, if a gasket should fail, air will go
into the unit instead of refrigerant coming out, eliminating the
impact of an underground leak.
Results
After multiple failures on previously installed Trane chillers at
its mine in Quebec, Agnico Eagle met with Trane to resolve issues and
improve their systems. Regaining confidence in the Trane units and the
company’s ability to troubleshoot problems, Agnico Eagle installed
five new 1300-ton Trane CenTraVac™ chillers in their mine extension.
“We wanted to have a meeting with Trane to be sure we were in business
together,” said Christian Quirion, maintenance manager, Agnico Eagle.
“We met with the Trane engineers. There was a lot of expertise in the
room and the teamwork was good.
“With the old 1000-ton
chillers, we were running them more safely at 75 percent, but with
less capacity, we were always running on the edge. With the new
chillers, we will have four running and one spare. We are farther from
the edge and have more flexibility and efficiency. Modifications have
been done with the new chillers. They are built stronger and there is
no possibility of surge. There are no mechanical issues with the new
chillers. They are running well.”
“Trane took problems in
hand and corrected them,” Quirion added. ”They did the job correctly
and we are now satisfied. It didn’t go smoothly early on, but the last
step was perfect.”